Record the original and revised quantities
Save the original sheet number, issue date, and measured boundary. On the revision, check the scale again and identify changes to area and thickness before comparing totals. Record additions and deductions separately when the revised scope moves concrete between locations or mixes.
Example of a net addition
A slab extension at the same thickness
Original 900 sq ft. Revised 1,020 sq ft. The additional 120 sq ft at 6 in. thick adds 2.2 cu yd before any ordering allowance.
Put the net quantity, revision date, and relevant photos or field notes in the change record so the next reviewer can reproduce the comparison.