Find the slab-to-beam overlap
Check where the structural section measures the beam depth from. If your slab takeoff already covers the top of the beam, count only the beam depth below the slab. Use net beam lengths or deduct overlaps at intersections before you multiply.
Work the numbers
Example foundation
Slab 1,800 sq ft × 0.5 ft ÷ 27 = 33.3 cu yd.
Grade beams 120 net ft × 1.5 ft wide × 1 ft below the slab ÷ 27 = 6.7 cu yd.
Total measured concrete 40.0 cu yd before ordering allowance.
Check the civil plan separately for approach, parking, and sidewalk scope. Waco publishes distinct submittal checklists for building and parking lot work.